DENMARK, ROSKILDE FJORD LINK
11/30/2018

 

The project continues to be on track for an early completion at the end of July 2019. The high bridge is 60% complete and erection of segments is progressing at a fast pace given that two work shifts are happening daily. precasting of segments in Poland is on-going and 102 segments remain to be cast out of a total of 492. As for the remaining 7.5 Km of roadway under construction, asphalt can already be seen on both sides of the Fjord connection. Part of the new motorway will become more visible in the landscape during the next weeks as paving on both sides of the fjord progresses